PROJECT
Kut- Butaira
PROJECT CODE IP-114
Long46.38º Lat32.52º
Start:
Duration:
Rehabilitation start year: 2018
Rehabilitation end year: 2020
Reclamation start year: 2021
Reclamation end year: 2027
Is OpportunityIs EmergencyIs ApportenantIs CandidateIs ObsoleteChecked
Project Cost (USD): $604,795,324
Partial Project Cost (USD)
Project Cost (USD): $604,795,324
Governorate: Wasit-Missan
River: Tigris
Location: On the left bank of the Tigris River,15 km northeast of Kut
Category: Irrigation and Drainage Projects
Sub category: Major Reclamation
Sector: Current and future agriculture developments and productivity;
Type: Land reclamation, implementation/expansion of irrigation projects
Opportunity type: Construction
Source: Water Resources Development Strategies 2010-2014. Page 21. Wasit PDS 2010-2014.
Source of fund: GoI
Original source: MoWR
Implementing agency: MoWR
Status: Partially Developed