PROJECT
Section 3 of the (GGD) Network
PROJECT CODE DR-028
Longº Latº
Start:
Duration:
Rehabilitation start year:
Rehabilitation end year:
Reclamation start year:
Reclamation end year:
Is OpportunityIs EmergencyIs ApportenantIs CandidateIs ObsoleteChecked
Project Cost (USD): $191,408
Partial Project Cost (USD)
REH off border irrigation (USD):
RECL off border irrigation (USD):
REH off border drainage (USD):
RECL off border drainage (USD):
REH off farm irrigation (USD):
RECL off farm irrigation (USD):
REH off farm drainage (USD):
RECL off farm drainage (USD):
REH off farm other (USD):
RECL off farm other (USD):
REH on farm irrigation (USD):
RECL on farm irrigation (USD):
REH on farm drainage (USD):
RECL on farm drainage (USD):
REH on farm other (USD):
RECL on farm other (USD):
Project Cost (USD): $191,408
Governorate: WASIT
River: Tigris
Location: Zone 1 – part of the Great Gharaf Drain Network
Category: Drainage Systems
Sub category: Main Drainage System
Sector: Drainage System;
Type: Infrastructures
Opportunity type: Operation & Mantainance
Source: MoWR
Source of fund: MoWR
Original source: NDS 2010-2014, pg 108
Implementing agency: MoWR
Status: Developed
Description
This section serves par to of the Middle Tigris Irrigation Project (estimated discharge 4 m^3/s). The project is under planning and design.
Needs
Operation and mantainancde is required.
Objective
O&M, Reuse of Drainage Water