PROJECT
Hadeetha
PROJECT CODE DAM-001
Long42.36º Lat34.21º
Start: 2015
Duration: 5
Rehabilitation start year:
Rehabilitation end year:
Reclamation start year:
Reclamation end year:
Is OpportunityIs EmergencyIs ApportenantIs CandidateIs ObsoleteChecked
Project Cost (USD): $5,000,000
Partial Project Cost (USD)
REH off border irrigation (USD):
RECL off border irrigation (USD):
REH off border drainage (USD):
RECL off border drainage (USD):
REH off farm irrigation (USD):
RECL off farm irrigation (USD):
REH off farm drainage (USD):
RECL off farm drainage (USD):
REH off farm other (USD):
RECL off farm other (USD):
REH on farm irrigation (USD):
RECL on farm irrigation (USD):
REH on farm drainage (USD):
RECL on farm drainage (USD):
REH on farm other (USD):
RECL on farm other (USD):
Project Cost (USD): $5,000,000
Governorate: ANBAR
River: Euphrates
Location:
Category: Dams
Sub category: Multy Purpose Dam
Sector: Hydro electricity;
Type: Electricity
Opportunity type: Operation & Mantainance
Source: MoWR
Source of fund: MoWR
Original source: MoWR
Implementing agency: MoWR
Status: Developed
Description
The dam is located in Anbar Governorate on Euphrates River, 7 Km North of Haditha Town, 140 km from the Syrian borders and at 250 km upstream of Baghdad. The dam is an embankment dam , 9.5 km long with maximum Height of 54 m , the dam was built using dolomite central core including an impervious central asphaltic diaphragm and a mixture of sand and gravel upstream and downstream shells with concrete upstream protection and rocks riprap downstream protection . the central core is founded on a grout curtain provided to control seepage and uplift pressure . the site Investigations and design were prepared by the Russian Survey and design Institute “HYDROPROJECT “ in 1978 . The dam was completed and Commissioned in 1985.
Needs
Abnormal incidents were observed in the dam from its first commissioning, they are wet area, increase of water level in some Piezometers at the d/s side of the dam, and they are even higher than the water levels of u/s side on the same alignment. Therefore Detailed inspection of evaluation of the status and problems by a qualified panel of experts is needed. Since the dam and appurtenant structures are not evaluated for long time, overall evaluation needs to be carried out either by specialized consultant or by a panel of experts.
Objective
The dam was constructed as a multipurpose project for the following Objectives: Flood Control of Euphrates River to a certain extents. Storage Of Water for downstream Irrigation demands and other uses. Electric Power Generation. Development of Tourist facilities and Fisheries
Screening
yes