PROJECT

Heet-2

PROJECT CODE DAM-045

Long42.80º Lat33.66º

Start: 2035

Duration: 4

Rehabilitation start year:

Rehabilitation end year:

Reclamation start year:

Reclamation end year:

ZIs OpportunityVIs EmergencyVIs ApportenantVIs CandidateVIs ObsoleteZChecked

Project Cost (USD): $87,971,678
Partial Project Cost (USD)
REH off border irrigation (USD):
RECL off border irrigation (USD):
REH off border drainage (USD):
RECL off border drainage (USD):
REH off farm irrigation (USD):
RECL off farm irrigation (USD):
REH off farm drainage (USD):
RECL off farm drainage (USD):
REH off farm other (USD):
RECL off farm other (USD):
REH on farm irrigation (USD):
RECL on farm irrigation (USD):
REH on farm drainage (USD):
RECL on farm drainage (USD):
REH on farm other (USD):
RECL on farm other (USD):

Project Cost (USD): $87,971,678

Governorate: ANBAR

River: Euphrates

Location:

Category: Dams

Sub category: HydroPower Dam

Sector: Hydro electricity;

Type: Electricity

Opportunity type: Study

Source: SWLRI Phase I

Source of fund:

Original source: MoInd

Implementing agency: MoEl

Status: Proposed/Planned

Heet-2

Description

At the Dam hydroscheme

Needs

The dam will need to have an Installed capacity of 17 MW and will generate 104 GWh/year

Objective

The total energy generated in Iraq in 2035 will account for 47.4 Billion kWh/year. Heet-2 could contribute to cover up to 0.22%

Screening

yes

Beneficiaries