PROJECT CODE DAM-022
Long43.30º Lat36.08º
Start: 2035
Duration: 5
Rehabilitation start year:
Rehabilitation end year:
Reclamation start year:
Reclamation end year:
Is OpportunityIs EmergencyIs ApportenantIs CandidateIs ObsoleteChecked
Project Cost (USD): $81,743,265
Partial Project Cost (USD)
REH off border irrigation (USD):
RECL off border irrigation (USD):
REH off border drainage (USD):
RECL off border drainage (USD):
REH off farm irrigation (USD):
RECL off farm irrigation (USD):
REH off farm drainage (USD):
RECL off farm drainage (USD):
REH off farm other (USD):
RECL off farm other (USD):
REH on farm irrigation (USD):
RECL on farm irrigation (USD):
REH on farm drainage (USD):
RECL on farm drainage (USD):
REH on farm other (USD):
RECL on farm other (USD):
Project Cost (USD): $81,743,265
Governorate: NINAWA
River: Tigris
Location:
Category: Dams
Sub category: HydroPower Dam
Sector: Hydro electricity;
Type: Electricity
Opportunity type: Study
Source:
Source of fund:
Original source:
Implementing agency: MoEl
Status:
Description
Diversion Dam
Needs
During the period 2025 – 2030 it is estimated that the additional energy demand will be 61925 GWh and the addtional Power Demand 8444 MW.
Objective
It is assumed that during this period, 14% of the demand could be covered by hydropower. Nimrud Dam could contribute to cover up to 6.8% of such additional demand.
Screening
yes